BILL OF QUANTITIES FOR CONSTRUCTING A MATERNITY WARD AT BUTOGOTA PARISH HEALTH CENTRE II

S/N

Item

Amount

Unit rate (UGx)

Total (UGx)

1

Element one: clearance

(a)

Setting out points for construction

-

-

(b)

Trench excavation as it is directed by the engineer

175 m3

3,200 each

560,000

2

Element two: lay out of the structure according to the drawing

(a)

Bricks for both foundation work and structure wall work

52 bricks/m2

24,300 bricks

400 each

9,720,000

(b)

Sand for both brick work and finishing work

384 m3

180,000 each trip (8m3 per trip)

8,640,000

(c)

Gravel, well graded aggregates should be made for both blinding and beam work

18 trips

150,000 each

2,700,000

(d)

Hard cores filling for slab casting

12 trips

120,000 each

1,440,000

(e)

Reinforce bars (11.6 m x 16 mm diameter) for both columns and beam work

57 pieces

42,000 each

2,394,000

(f)

Reinforcement links for all work

93 pieces

4,500 each

418,500

(g)

Binding wire for all works

2 rolls

110,000 each

220,000

(h)

Cement

50 Kgs/bag

203 bags

35,000 each

7,105,000

(i)

9*1cm timber for making form work

68 pieces

10,000 each

680,000

(j)

Form work nails

15 Kgs

5,500 each

82,500

3

Element three: scaffolding

(a)

Standing poles (props) for scaffold

54 poles

8,000 each

432,000

(b)

Standing poles for supporting the plate form

39 poles

6,000 each

234,000

(c)

Offcuts for making the platform

44 pieces

3,500 each

154,000

(d)

Scaffolds nails

12 Kgs

5,500 each

66,000

(e)

Rope rolls

12 rolls

6,000 each

72,000

4

Element four: roofing

(a)

3cm*4cm timber for wall plates

57 pieces

5,000 each

285,000

(b)

6cm*2cm timber for tie beams and king posts of the structure

84 pieces

6,000 each

504,000

(c)

4cm*2cm timber for planes and struts

1246 pieces

4,000 each

4,984,000

(d)

Iron plates

144 sheets

45,000 each

6,480,000

(e)

Ridges for the structure

38 pieces

15,000 each

570,000

(f)

Valleys for the hipped roof

9 pieces

15,000 each

135,000

(g)

Roofing nails

24 Kgs

6,500 each

156,000

(h)

Roofing nails rubbers (washers)

32 packets

12,000 each

384,000

(i)

Roofing phynes

15 Kgs

2,500 each

37,500

5

Element five: shuttering

(a)

Metal doors

3 doors

475,000 each

1,425,000

(b)

Metal windows

11 windows

280,000 each

3,080,000

(c)

Metal shower window

2 shower windows

130,000 each

260,000

(d)

Internal wooden doors

8 doors

350,000 each

2,800,000

(e)

Expanded mesh

14 rolls

30,000 each

420,000

6

Element six: finishing

(a)

Floor tiles for shower rooms

42 m2

42,000/m2

1,764,000

(b)

Wall tiles for sluice room and shower

28 m2

28,000/m2

784,000

(c)

Floor tiles for shower room

12 m2

18,000/m2

216,000

(d)

Adhesive cement

50 Kg/bag

7 bags

32,000 each bag

224,000

(e)

Grout for filling

10 Kg/sack

10 sacks

10,000 each sack

100,000

7

Element seven: ceiling

(a)

Expanded mesh to some rooms

27 rolls

30,000 each

810,000

(b)

Nails for mesh

16 Kgs

6,500 each

104,000

(c)

Wood nail for all work

75 Kgs

5,500 each

412,500

8

Element eight: painting

(e)

Sand paper

50 m2

2,500/m2

125,000

(f)

Damp proof material

32 m2

3,000/m2

96,000

(g)

Steel wall

3 rolls

10,000 each

30,000

(h)

Window glasses

34 glasses

15,000 each

510,000

(i)

Putty for fixing glasses

17 Kgs

7,300/Kg

124,100

(j)

Silicon

3 tins

15,000 each

45,000

(k)

Under coat paint

13 cans

73,000 each

949,000

(l)

Internal weather guard paint

3 buckets

294,000 each

882,000

(m)

External weather guard paint

2 buckets

294,000 each

588,000

Materials total

64,202,100

Labour (26 workers including engineer)

25,040,837

Monitoring and evaluation

3,500,000

Subtotal

92,742,937

Contingency

20%

18,548,587.40

Estimated provision for electrification and plumbing works

10%

9,274,293.70

Total (UGx)

120,565,818

Total (£)

26,209.94

Add a Comment

photo

Anonymous

Backed with £10.00 On Jan 23, 2020

photo

Anonymous

Backed On Jan 03, 2020 Amount Hidden

photo

Anonymous

Backed with £20.00 On Dec 08, 2019

photo

Keep up the good work!

Gloria Padmaperuma

Backed with £50.00 On Dec 08, 2019

photo

God bless

Anonymous

Backed On Nov 05, 2019 Amount Hidden

photo

Mil gracias por darme la oportunidad de hacer el bien.

Anonymous

Backed On Oct 13, 2019 Amount Hidden

photo

What a brave and wonderful thing that you are doing Alenjandra! Go bless you all.

Anonymous

Backed with £100.00 On Oct 07, 2019

photo

Evangelist Ohaejesi

Backed with £733.00 On Oct 07, 2019

photo

Happy to help in saving babies’ lives.

Anonymous

Backed with £100.00 On Oct 01, 2019

photo

So happy to support such a worthwhile cause

Anonymous

Backed On Sep 30, 2019 Amount Hidden

Show more donors
Add a Comment

photo

Alejandra H Giron

Missionary

flag Butogota, ug

Send a message

https://www.facebook.com/Mission-Uganda-107779813918114/

photo

Manuel Rios

Since Jul 07, 2019

Create support campaign

Not Ready to Donate?

Did you know a 10 second Facebook share raises an average of £25?

Share on